Location Identification & TEFR
SPV (50:50 JV) prepares Techno-Economic Feasibility Report, finalises location with State Govt, and applies to NSbM through the Implementing Agency. NSbM grants in-principle approval based on TEFR - no financial commitment yet.
Anchor Shipyard Selection & DPR Prep
SPV onboards anchor shipyard(s) via EOI or direct outreach, secures investment commitments, and prepares the cluster DPR (internal infra, channel & basin, breakwater, common facilities). Land allocated by State Govt at ₹1.
NSbM Review & Grant
IEA verifies DPR for technical feasibility & cost reasonableness. IA forwards to NSbM with appraisal. Inter-Ministerial Governing Board decides; capital assistance communicated to SPV. Must submit within 24 months of in-principle approval.
Operationalisation & Fund Release
SPV initiates site development. 100% capital assistance released in milestone tranches (15%-30%-35%-20%) subject to IPMA physical verification and Fund Utilisation Certificates.