In-Principle & Final Approval Process

The four-phase journey from location identification to fund release, governed by the SPV, DGMA / IEA, and the National Shipbuilding Mission (NSbM).

Four-Phase Approval Journey
Phase 1 · In-Principle Approval
Location Identification & TEFR

SPV (50:50 JV) prepares Techno-Economic Feasibility Report, finalises location with State Govt, and applies to NSbM through the Implementing Agency. NSbM grants in-principle approval based on TEFR - no financial commitment yet.

Phase 2 · Anchor & DPR
Anchor Shipyard Selection & DPR Prep

SPV onboards anchor shipyard(s) via EOI or direct outreach, secures investment commitments, and prepares the cluster DPR (internal infra, channel & basin, breakwater, common facilities). Land allocated by State Govt at ₹1.

Phase 3 · Final Approval
NSbM Review & Grant

IEA verifies DPR for technical feasibility & cost reasonableness. IA forwards to NSbM with appraisal. Inter-Ministerial Governing Board decides; capital assistance communicated to SPV. Must submit within 24 months of in-principle approval.

Phase 4 · Site Development
Operationalisation & Fund Release

SPV initiates site development. 100% capital assistance released in milestone tranches (15%-30%-35%-20%) subject to IPMA physical verification and Fund Utilisation Certificates.

100% Capital Support - Five Eligible Categories
1. Common Maritime Assets
Barges, floating cranes, pontoons, tugs - registered under SPV for collective use (₹500 Cr indicative)
2. Internal Infrastructure
Internal roads, rail links, water, power distribution, drainage, sewage, firefighting (₹1,100 Cr)
3. Channel & Basin
Breakwaters/wave breakers (₹1,100 Cr), channel & basin development, dredging (₹500 Cr)
4. Social Infrastructure
Worker accommodation, mess, medical, recreational areas, civic waste treatment
5. Capability Centres
Regional shipbuilding capability development centres (₹110 Cr - training, R&D)
Excluded
SPV human resources, O&M expenses, maintenance dredging, land costs
Assistance per cluster ≈ ₹3,310 Cr against a total scheme overlay of ₹9,930 Cr - funding approximately 3 clusters. Each cluster targets ~1.2 million GT/annum (≈2 million DWT), contributing to the 3.6 million GT that greenfield clusters are expected to add by 2047.